On June 6, 2024, Plymouth Housing sent the City of Redmond’s Planning Department an email, asking the city to make a determination about the site class of the Cleveland Street homeless building site. Instead of following the scientific evidence, Plymouth Housing was asking the city’s planning department to pick a site type. 

“There is some conflict between them as to whether the 16725 Cleveland St site is a site class D or site class F. Our geotech report currently indicates it is class D and our structural engineer is concerned about that finding and thinks it’s an F. Would you be willing to take a look at our geotechnical study to make a determination about how the City would interpret the findings? We are at a place where we’d like to avoid any schedule delays that might occur if we were to pick one and move forward (and then be wrong and need to revise). “

A site class F raises legit liquefaction concerns. Liquefaction refers to the potential for soil to lose its strength during an earthquake. If Plymouth Housing errors on the safety side, they would listen to the structural engineers’ concerns. Rather, they wanted to find a short cut. Luckily, the staff at the planning department told them, “Your geotechnical engineer will determine and list the site class rating in their report. City staff does not make this determination. “

In the final submitted Geotech Study, it states that although the soil was originally classified as Site Class D, upon further investigation using the King County Liquefaction Susceptibility map, the site was found to have a “low to moderate” risk of liquefaction. “These soils were deemed potentially liquefiable; accordingly, the site classification is Class F, requiring a site specific seismic response spectra be developed.“

Full Geotech Study:

Plymouth Housing’s email to City of Redmond: